Real Estate: Making Owners and General Contractors Personally Liable to Subcontractor, Laborer or Materialman


     Virginia Code §43-11 provides a way for owners or general contractors to be made personally liable to subcontractor, laborer or materialman if notice is appropriately given, and if the payer makes payment to the owing party without paying the notifying creditor. Specifically, §43-11 (2) states that:
     “…if such subcontractor, or person furnishing labor or material shall at any time after the work is done or material furnished by him and before the expiration of thirty days from the time such building or structure is completed or the work thereon otherwise terminated furnish the owner thereof or his agent and also the general contractor, or the general contractor alone in case he is the only one notified, with a second notice stating a correct account, verified by affidavit, of his actual claim against the general contractor or subcontractor, for work done or materials furnished and of the amount due, then the owner, or the general contractor, if he alone was notified, shall be personally liable to the claimant for the actual amount due to the subcontractor or persons furnishing labor or material by the general contractor or subcontractor, provided the same does not exceed the sum in which the owner is indebted to the general contractor at the time the second notice is given or may thereafter become indebted by virtue of his contract with the general contractor, or in case the general contractor alone is notified the sum in which he is indebted to the subcontractor at the time the second notice is given or may thereafter become indebted by virtue of his contract with the general contractor. But the amount which a person supplying labor or material to a subcontractor can claim shall not exceed the amount for which such subcontractor could file his claim.”
     The notices referred to in this code section are commonly referred to in the industry as “42-11 letters”. We have experienced attorneys and staff who can examine title, file mechanic’s liens, and litigate to enforce the same. If you have a need, please call us.





Monday, July 15, 2013

Real Estate: Perfecting Mechanic's Liens

     In recent editions of Creditor News we have been discussing the benefits of using real estate to improve creditors’ positions. Last month we began a discussion of the benefits of using mechanic’s liens to aid in the collection of your debt.
     Virginia Code §§43-4, 43-7 and 43-9 provide for the perfection of the lien by general contractors, subcontractors, and laborers and suppliers. In each section the creditor must file a memorandum of lien at any time after the work is commenced or material furnished, but not later than 90 days from the last day of the month in which he last performs labor or furnishes material, and in no event later than 90 days from the time such building, structure, etc., is completed, or the work thereon otherwise terminated. The memorandum must contain specific information as set forth in the code (and there are forms in the code), and must be filed in the clerk's office in the county or city in which the building, structure etc., or any part thereof is located. The memorandum shall show the names of the owner of the property sought to be charged, and of the claimant of the lien, the amount and consideration of his claim, and the time or times when the same is or will be due and payable, verified by the oath of the claimant, or his agent, including a statement declaring his intention to claim the benefit of the lien, and giving a brief description of the property on which he claims a lien.
     We have experienced attorneys and staff who can examine title, file mechanic’s liens, and litigate to enforce the same.