Real Estate: Suit to Enforce Mechanic's Liens

       In prior blogs, we have been discussing the benefits of using real estate to improve creditors’ positions. We have discussed perfection of liens. In this blog we will discuss suit to enforce mechanic’s liens. 
     Virginia Code §43-17 provides that no suit to enforce a mechanic’s lien can be brought: 
     “…after six months from the time when the memorandum of lien was recorded or after sixty days from the time the building, structure or railroad was completed or the work thereon otherwise terminated, whichever time shall last occur; provided, however, that the filing of a petition to enforce any such lien in any suit wherein such petition may be properly filed shall be regarded as the institution of a suit under this section; and, provided further, that nothing herein shall extend the time within which such lien may be perfected.” 
     Virginia Code §43-17.1 provides that: 
     “Any party, having an interest in real property against which a lien has been filed, may, upon a showing of good cause, petition the court of equity having jurisdiction wherein the building, structure, other property, or railroad is located to hold a hearing to determine the validity of any perfected lien on the property. After reasonable notice to the lien claimant and any party to whom the benefit of the lien would inure and who has given notice as provided in § 43-18 of the Code of Virginia, the court shall hold a hearing and determine the validity of the lien. If the court finds that the lien is invalid, it shall forthwith order that the memorandum or notice of lien be released from record.” 
     Virginia Code §43-18 provides: 
     “The perfected lien of a general contractor on any building or structure shall inure to the benefit of any subcontractor, and of any person performing labor or furnishing materials to a subcontractor who has not perfected a lien on such building or structure, provided such subcontractor, or person performing labor or furnishing materials shall give written notice of his claim against the general contractor, or subcontractor, as the case may be, to the owner or his agent before the amount of such lien is actually paid off or discharged.” 
     We have experienced attorneys and staff who can examine title, file mechanic’s liens, and litigate to enforce the same.


Monday, April 10, 2017

Real Estate: Criminal Liability for Misuse of Construction Funds

     Virginia Code §43-13 provides that funds paid to a general contractor or subcontractor must be used to pay persons performing labor or furnishing material. Any contractor or subcontractor or any officer, director or employee of such contractor or subcontractor who, with intent to defraud, retain or use the funds, or any part thereof, paid by the owner or his agent, shall be guilty of larceny in appropriating such funds for any other use while any amount for which the contractor or subcontractor may be liable or become liable under his contract for such labor or materials remains unpaid, and may be prosecuted upon complaint of any person or persons who have not been fully paid any amount due them.
     The use by any such contractor or subcontractor or any officer, director or employee of such contractor or subcontractor of any moneys paid under the contract, before paying all amounts due or to become due for labor performed or material furnished for such building or structure, for any other purpose than paying such amounts, shall be prima facie evidence of intent to defraud.

Monday, May 11, 2015

Real Estate: Using Mechanic's Liens to Secure an Interest in Real Estate


     In prior editions of Creditor News (you can view these at www.lawplc.com) we have been discussing the benefits of using real estate to improve creditors’ positions. As I have emphasized, properly securing debts through real estate could make the difference between collecting the funds and incurring a loss. In this blog, we will begin a review of the benefits of using mechanic’s liens to aid in the collection of your debt.
     Virginia Code §43-3 et. seq. provides for special procedures for the collection of unpaid bills related to work performed on, or products supplied for, real estate. §43-3 A states:
      “All persons performing labor or furnishing materials of the value of $150 or more … for the construction, removal, repair or improvement of any building or structure permanently annexed to the freehold … shall have a lien, if perfected as hereinafter provided, upon such building or structure, and so much land therewith as shall be necessary for the convenient use and enjoyment thereof … subject to the provisions of § 43-20. But when the claim is for repairs or improvements to existing structures only, no lien shall attach to the property repaired or improved unless such repairs or improvements were ordered or authorized by the owner, or his agent.”
     Virginia Code §43-3 B provides for special rules regarding condominiums.
     Virginia Code §§43-4, 43-7 and 43-9 provide for the perfection of the lien by general contractors, subcontractors, and laborers and suppliers. We will explore this more in another blog.
     We have experienced attorneys and staff who can examine title, file mechanic’s liens, and litigate to enforce the same.



Monday, September 9, 2013

Real Estate: Suit to Enforce Mechanic's Liens

     In recent editions of Creditor News (which can be viewed at http://lawplc.com) we have been discussing the benefits of using real estate to improve creditors’ positions. Last month we discussed perfection of liens. This month we will discuss suit to enforce mechanic’s liens.
     Virginia Code §43-17 provides that no suit to enforce a mechanic’s lien can be brought:
“…after six months from the time when the memorandum of lien was recorded or after sixty days from the time the building, structure or railroad was completed or the work thereon otherwise terminated, whichever time shall last occur; provided, however, that the filing of a petition to enforce any such lien in any suit wherein such petition may be properly filed shall be regarded as the institution of a suit under this section; and, provided further, that nothing herein shall extend the time within which such lien may be perfected.”
     Virginia Code §43-17.1 provides that:
“Any party, having an interest in real property against which a lien has been filed, may, upon a showing of good cause, petition the court of equity having jurisdiction wherein the building, structure, other property, or railroad is located to hold a hearing to determine the validity of any perfected lien on the property. After reasonable notice to the lien claimant and any party to whom the benefit of the lien would inure and who has given notice as provided in § 43-18 of the Code of Virginia, the court shall hold a hearing and determine the validity of the lien. If the court finds that the lien is invalid, it shall forthwith order that the memorandum or notice of lien be released from record.”
     Virginia Code §43-18 provides:
“The perfected lien of a general contractor on any building or structure shall inure to the benefit of any subcontractor, and of any person performing labor or furnishing materials to a subcontractor who has not perfected a lien on such building or structure, provided such subcontractor, or person performing labor or furnishing materials shall give written notice of his claim against the general contractor, or subcontractor, as the case may be, to the owner or his agent before the amount of such lien is actually paid off or discharged.”
     We have experienced attorneys and staff who can examine title, file mechanic’s liens, and litigate to enforce the same.