Monday, May 20, 2019

Real Estate: Suit to Enforce Mechanic's Liens

       In prior blogs, we have been discussing the benefits of using real estate to improve creditors’ positions. We have discussed perfection of liens. In this blog we will discuss suit to enforce mechanic’s liens. 
     Virginia Code §43-17 provides that no suit to enforce a mechanic’s lien can be brought: 
     “…after six months from the time when the memorandum of lien was recorded or after sixty days from the time the building, structure or railroad was completed or the work thereon otherwise terminated, whichever time shall last occur; provided, however, that the filing of a petition to enforce any such lien in any suit wherein such petition may be properly filed shall be regarded as the institution of a suit under this section; and, provided further, that nothing herein shall extend the time within which such lien may be perfected.” 
     Virginia Code §43-17.1 provides that: 
     “Any party, having an interest in real property against which a lien has been filed, may, upon a showing of good cause, petition the court of equity having jurisdiction wherein the building, structure, other property, or railroad is located to hold a hearing to determine the validity of any perfected lien on the property. After reasonable notice to the lien claimant and any party to whom the benefit of the lien would inure and who has given notice as provided in § 43-18 of the Code of Virginia, the court shall hold a hearing and determine the validity of the lien. If the court finds that the lien is invalid, it shall forthwith order that the memorandum or notice of lien be released from record.” 
     Virginia Code §43-18 provides: 
     “The perfected lien of a general contractor on any building or structure shall inure to the benefit of any subcontractor, and of any person performing labor or furnishing materials to a subcontractor who has not perfected a lien on such building or structure, provided such subcontractor, or person performing labor or furnishing materials shall give written notice of his claim against the general contractor, or subcontractor, as the case may be, to the owner or his agent before the amount of such lien is actually paid off or discharged.” 
     We have experienced attorneys and staff who can examine title, file mechanic’s liens, and litigate to enforce the same.