          In a previous blog, I began discussing the Virginia Property Owners’ Association Act. 
     The Act specifically provides for remedies outside of the more common remedy of filing suit for the amount owed and receiving a judgment. A memorandum of lien to a holder of a credit line deed of trust under the Act is given in the same fashion as if the association’s lien were a judgment. Under the Act, the association can file for and perfect a lien against the homeowner that is prior to all other subsequent liens and encumbrances except real estate tax liens, liens and encumbrances recorded prior to the recordation of the declaration, and sums unpaid on and owing under any mortgage or deed of trust recorded prior to perfection of this lien. 
     To perfect the memorandum of lien, the association must file with the clerk of the circuit court in the county or city in which the development is situated a memorandum verified by the oath of the principal officer of the association or another officer provided for in the declaration. The memorandum must be filed within 12 months from the first assessment became due and payable. Additionally, prior to filing a memorandum of lien, a written notice must be sent to the property owner by certified mail, at the owner’s last known address, informing the owner that the lien will be filed in the circuit court clerk’s office at least 10 days before the actual filing date of the lien. The memorandum must name the development, describe the lot, name the person(s) constituting the owners of the lot, list the amount of unpaid assessments currently due or past due relative to such lot together with the date when each fell due, list the date of issuance of the memorandum, name the association with a name and address of the contact for the person to contact to arrange for payment or release of the lien, and state that the association is obtaining a lien in accordance with the provisions of the Virginia Property Owners’ Association act as set forth in Chapter 26 (section 55-508 et seq.) of Title 55. 
     The Act provides that a judgment or decree in this action must include, without limitation, reimbursement for costs and reasonable attorney’s fees for the prevailing party. Also, if the association prevails, it may also recover interest at the legal rate for the sums secured by the lien from the time each sum became due and payable. If the owner then satisfies the debt, the lien must be released, and failure to release the lien results in a penalty. 
     Once a lien has been perfected, the association must enforce the lien within 36 months from the time when the memorandum of lien was recorded. This time period cannot be extended. 
     In a future blog, I will discuss foreclosure on a lien.


Monday, October 10, 2016

Collection: Mechanics Lien voided by Old Work

     Mechanic’s liens are strictly governed by statutory law. This fact is well illustrated in the case of Johnson v. Tadlock. In Johnson the Fairfax County Circuit Court ruled that a mechanic's lien that included work performed before the 150-day statutory window was invalid in its entirety. Under the mechanic's lien statute, a memorandum of lien should not include any sums due for labor and materials furnished more than 150 days prior to the last day of work. However, the Court's decision in Johnson appears to be the first in which a Circuit Court has struck an entire lien based on the inclusion of stale work.
     In Johnson, the Court found as fact that a workman filed a mechanic's lien for $15,500 for various work, including lot clearance, removal of trees and installation of a storm drainage system and caissons. The property owner sought to have the lien released based on its inclusion of stale work. A portion of the lien (amounting to at least $1,500) was for work clearly performed within the 150-day statutory period. The property owner asserted that all or a part of the remainder of the work was performed more than 150 days prior to the workman's last day on the job.
     The Court ruled that the inclusion of a stale claim tainted the entire lien. The Court cited language in the mechanic's lien statute "no memorandum... shall include ....," to support his position. The Court pointed out that mechanic's liens are "creatures of statute" and therefore need to conform strictly to their statutory requirements. Accordingly, the court refused to remove the improper portions of the claim and rule on the proper portion of the claim - it survived or perished in its totality.
     The lesson of Johnson, as the lesson is in so many cases, obtain competent legal advise and representation in pursuing mechanic's lien claims.

Monday, August 29, 2016

Real Estate: The Virginia Property Owners' Association Act - Memorandums of Lien

      In a previous blog, I began discussing the Virginia Property Owners’ Association Act.
     The Act specifically provides for remedies outside of the more common remedy of filing suit for the amount owed and receiving a judgment. A memorandum of lien to a holder of a credit line deed of trust under the Act is given in the same fashion as if the association’s lien were a judgment. Under the Act, the association can file for and perfect a lien against the homeowner that is prior to all other subsequent liens and encumbrances except real estate tax liens, liens and encumbrances recorded prior to the recordation of the declaration, and sums unpaid on and owing under any mortgage or deed of trust recorded prior to perfection of this lien.
     To perfect the memorandum of lien, the association must file with the clerk of the circuit court in the county or city in which the development is situated a memorandum verified by the oath of the principal officer of the association or another officer provided for in the declaration. The memorandum must be filed within 12 months from the first assessment became due and payable. Additionally, prior to filing a memorandum of lien, a written notice must be sent to the property owner by certified mail, at the owner’s last known address, informing the owner that the lien will be filed in the circuit court clerk’s office at least 10 days before the actual filing date of the lien. The memorandum must name the development, describe the lot, name the person(s) constituting the owners of the lot, list the amount of unpaid assessments currently due or past due relative to such lot together with the date when each fell due, list the date of issuance of the memorandum, name the association with a name and address of the contact for the person to contact to arrange for payment or release of the lien, and state that the association is obtaining a lien in accordance with the provisions of the Virginia Property Owners’ Association act as set forth in Chapter 26 (section 55-508 et seq.) of Title 55.
     The Act provides that a judgment or decree in this action must include, without limitation, reimbursement for costs and reasonable attorney’s fees for the prevailing party. Also, if the association prevails, it may also recover interest at the legal rate for the sums secured by the lien from the time each sum became due and payable. If the owner then satisfies the debt, the lien must be released, and failure to release the lien results in a penalty.
     Once a lien has been perfected, the association must enforce the lien within 36 months from the time when the memorandum of lien was recorded. This time period cannot be extended.
     In a future blog, I will discuss foreclosure on a lien.





Monday, August 3, 2015

Real Estate: Suit to Enforce Mechanic's Liens


     In recent blogs we have been discussing the benefits of using real estate to improve creditors’ positions. Recently we discussed perfection of liens. In this blog we will discuss suit to enforce mechanic’s liens.
     Virginia Code §43-17 provides that no suit to enforce a mechanic’s lien can be brought:
“…after six months from the time when the memorandum of lien was recorded or after sixty days from the time the building, structure or railroad was completed or the work thereon otherwise terminated, whichever time shall last occur; provided, however, that the filing of a petition to enforce any such lien in any suit wherein such petition may be properly filed shall be regarded as the institution of a suit under this section; and, provided further, that nothing herein shall extend the time within which such lien may be perfected.”
     Virginia Code §43-17.1 provides that:
“Any party, having an interest in real property against which a lien has been filed, may, upon a showing of good cause, petition the court of equity having jurisdiction wherein the building, structure, other property, or railroad is located to hold a hearing to determine the validity of any perfected lien on the property. After reasonable notice to the lien claimant and any party to whom the benefit of the lien would inure and who has given notice as provided in § 43-18 of the Code of Virginia, the court shall hold a hearing and determine the validity of the lien. If the court finds that the lien is invalid, it shall forthwith order that the memorandum or notice of lien be released from record.”
     Virginia Code §43-18 provides:
“The perfected lien of a general contractor on any building or structure shall inure to the benefit of any subcontractor, and of any person performing labor or furnishing materials to a subcontractor who has not perfected a lien on such building or structure, provided such subcontractor, or person performing labor or furnishing materials shall give written notice of his claim against the general contractor, or subcontractor, as the case may be, to the owner or his agent before the amount of such lien is actually paid off or discharged.”
     We have experienced attorneys and staff who can examine title, file mechanic’s liens, and litigate to enforce the same.



Monday, June 8, 2015

Real Estate: Perfecting Mechanic's Liens


     In recent blogs we have been discussing the benefits of using real estate to improve creditors’ positions. On a previous blog we began a discussion of the benefits of using mechanic’s liens to aid in the collection of your debt.
     Virginia Code §§43-4, 43-7 and 43-9 provide for the perfection of the lien by general contractors, subcontractors, and laborers and suppliers. In each section the creditor must file a memorandum of lien at any time after the work is commenced or material furnished, but not later than 90 days from the last day of the month in which he last performs labor or furnishes material, and in no event later than 90 days from the time such building, structure, etc., is completed, or the work thereon otherwise terminated. The memorandum must contain specific information as set forth in the code (and there are forms in the code), and must be filed in the clerk's office in the county or city in which the building, structure etc., or any part thereof is located. The memorandum shall show the names of the owner of the property sought to be charged, and of the claimant of the lien, the amount and consideration of his claim, and the time or times when the same is or will be due and payable, verified by the oath of the claimant, or his agent, including a statement declaring his intention to claim the benefit of the lien, and giving a brief description of the property on which he claims a lien.
     We have experienced attorneys and staff who can examine title, file mechanic’s liens, and litigate to enforce the same.










Monday, January 19, 2015

Real Estate: The Virginia Property Owners' Association Act - Foreclosing on Memorandum of Lien



     In the last issues of Creditor News, I discussed the provisions related to filing a memorandum of lien under the Virginia Property Owners’ Association Act.
     The Act provides: “At any time after perfecting the lien pursuant to this section, the property owners' association may sell the lot at public sale, subject to prior liens.” In order to conduct a nonjudicial foreclosure, the association must comply with the statutory requirements.
     The association must give notice to the lot owner prior to advertising the sale. The notice must include notice of: “(i) the debt secured by the perfected lien; (ii) the action required to satisfy the debt secured by the perfected lien; (iii) the date, not less than 60 days from the date the notice is given to the lot owner, by which the debt secured by the lien must be satisfied; and (iv) that failure to satisfy the debt secured by the lien on or before the date specified in the notice may result in the sale of the lot.” The notice must also inform the lot owner of the right to bring a court action in the circuit court of the county or city where the lot is located to assert the nonexistence of a debt or any other defense of the lot owner to the sale.
     If the lot owner (i) satisfies the debt secured by lien that is the subject of the nonjudicial foreclosure sale and (ii) pays all expenses and costs incurred in perfecting and enforcing the lien, including but not limited to advertising costs and reasonable attorneys' fees, then the sale is discontinued. However, if after 60 days and the lot owner has not made those payments, the association may appoint a trustee for the sale and advertise the sale. In addition to advertising the sale, the association must give written notice of the time, date and place of any proposed sale in execution of the lien, and including the name, address and telephone number of the trustee. That notice must be at least given to the owner, lienholders and their assigns by certified or registered mail 14 days prior to the sale.
     The association must advertise the sale in a newspaper in the city or county where the property will be sold. The advertisement must be in a section with legal notices or where the property being sold is generally advertised for sale. The advertisement must describe the property by address and general location and have information for the representative or an attorney who can respond to inquiries about the property with their name, address, and telephone number. The advertisement must be in the newspaper for four successive weeks, but if the lot is located in a city or county immediately contiguous to a city, publication of the advertisement for five different days is sufficient. The sale then must be held on any day after the last advertisement but not earlier than 8 days after the first advertisement and not more than 30 days after the last advertisement.
     Failure to comply with these and other requirements in the statute will render the sale of the property voidable by the court. The law firm of Lafayette, Ayers & Whitlock, PLC, represents homeowner’s associations and can handle memorandums of lien and foreclosure procedures.




Monday, December 22, 2014

Real Estate: The Virginia Property Owners’ Association Act – Memorandums of Lien

     Previously I began discussing the Virginia Property Owners’ Association Act.

     The Act specifically provides for remedies outside of the more common remedy of filing suit for the amount owed and receiving a judgment. A memorandum of lien to a holder of a credit line deed of trust under the Act is given in the same fashion as if the association’s lien were a judgment. Under the Act, the association can file for and perfect a lien against the homeowner that is prior to all other subsequent liens and encumbrances except real estate tax liens, liens and encumbrances recorded prior to the recordation of the declaration, and sums unpaid on and owing under any mortgage or deed of trust recorded prior to perfection of this lien.

     To perfect the memorandum of lien, the association must file with the clerk of the circuit court in the county or city in which the development is situated a memorandum verified by the oath of the principal officer of the association or another officer provided for in the declaration. The memorandum must be filed within 12 months from the first assessment became due and payable. Additionally, prior to filing a memorandum of lien, a written notice must be sent to the property owner by certified mail, at the owner’s last known address, informing the owner that the lien will be filed in the circuit court clerk’s office at least 10 days before the actual filing date of the lien. The memorandum must name the development, describe the lot, name the person(s) constituting the owners of the lot, list the amount of unpaid assessments currently due or past due relative to such lot together with the date when each fell due, list the date of issuance of the memorandum, name the association with a name and address of the contact for the person to contact to arrange for payment or release of the lien, and state that the association is obtaining a lien in accordance with the provisions of the Virginia Property Owners’ Association act as set forth in Chapter 26 (section 55-508 et seq.) of Title 55.

     The Act provides that a judgment or decree in this action must include, without limitation, reimbursement for costs and reasonable attorney’s fees for the prevailing party. Also, if the association prevails, it may also recover interest at the legal rate for the sums secured by the lien from the time each sum became due and payable. If the owner then satisfies the debt, the lien must be released, and failure to release the lien results in a penalty.

     Once a lien has been perfected, the association must enforce the lien within 36 months from the time when the memorandum of lien was recorded. This time period cannot be extended.