Mechanic’s liens are strictly governed by statutory law. This fact is well illustrated in the case of Johnson v. Tadlock. In Johnson the Fairfax County Circuit Court ruled that a mechanic's lien that included work performed before the 150-day statutory window was invalid in its entirety. Under the mechanic's lien statute, a memorandum of lien should not include any sums due for labor and materials furnished more than 150 days prior to the last day of work. However, the Court's decision in Johnson appears to be the first in which a Circuit Court has struck an entire lien based on the inclusion of stale work.
In Johnson, the Court found as fact that a workman filed a mechanic's lien for $15,500 for various work, including lot clearance, removal of trees and installation of a storm drainage system and caissons. The property owner sought to have the lien released based on its inclusion of stale work. A portion of the lien (amounting to at least $1,500) was for work clearly performed within the 150-day statutory period. The property owner asserted that all or a part of the remainder of the work was performed more than 150 days prior to the workman's last day on the job.
The Court ruled that the inclusion of a stale claim tainted the entire lien. The Court cited language in the mechanic's lien statute "no memorandum... shall include ....," to support his position. The Court pointed out that mechanic's liens are "creatures of statute" and therefore need to conform strictly to their statutory requirements. Accordingly, the court refused to remove the improper portions of the claim and rule on the proper portion of the claim - it survived or perished in its totality.
The lesson of Johnson, as the lesson is in so many cases, obtain competent legal advise and representation in pursuing mechanic's lien claims.
In Johnson, the Court found as fact that a workman filed a mechanic's lien for $15,500 for various work, including lot clearance, removal of trees and installation of a storm drainage system and caissons. The property owner sought to have the lien released based on its inclusion of stale work. A portion of the lien (amounting to at least $1,500) was for work clearly performed within the 150-day statutory period. The property owner asserted that all or a part of the remainder of the work was performed more than 150 days prior to the workman's last day on the job.
The Court ruled that the inclusion of a stale claim tainted the entire lien. The Court cited language in the mechanic's lien statute "no memorandum... shall include ....," to support his position. The Court pointed out that mechanic's liens are "creatures of statute" and therefore need to conform strictly to their statutory requirements. Accordingly, the court refused to remove the improper portions of the claim and rule on the proper portion of the claim - it survived or perished in its totality.
The lesson of Johnson, as the lesson is in so many cases, obtain competent legal advise and representation in pursuing mechanic's lien claims.
No comments:
Post a Comment